Utility service providers works in Euston Approaches

Work item: HS2-SCS-26-2905

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Hampstead Road, Lidlington Place, Stanhope Street
Worksite Name
Euston Approaches
Contractor
SCS JV
Type of works
Utility Works
Estimated Start Date
01/01/2026
Estimated End Date
30/09/2026

What we are doing

We are currently carrying out our works to remove all the utilities from Hampstead Road and redirect them across Granby Terrace bridge and over the retaining wall within our worksite. These works are required before we extend Hampstead Road bridge. After we extend Hampstead Road bridge, we will permanently reinstall the utilities back on to Hampstead Road.

The next phase of the utility diversion works, which began in January 2026, involves various utility service providers working within our site, as well as on Hampstead Road, Lidlington Place and Stanhope Street to complete the final connections and energise their networks.

Depending on where the work is carried out, the utility service providers will either use our existing traffic management on Hampstead Road or install their own. Any work taking place within our site will be done overnight, between 7pm and 7am as the work will obstruct our
internal haul road, and must be carried out after daily site activities are complete. Most work outside our site on Hampstead Road, Lidlington Place and Stanhope Street will also be carried out overnight and on some weekends.

Utility service providers typically work during these times to minimise traffic disruption as well as public interface on local roads.
There will be some utility service providers that will work during core hours, 8am to 6pm Monday to Friday.

We do not expect these works to be noisy, the utility service providers will use best practicable methods, and the work will be monitored closely to ensure they remain within the noise limits agreed with the local council.

We apologise for any inconvenience these works may cause.

HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.

 