Utilties work near Curzon Station
Work item: HS2-EW-OTH-UT-Ph1-Bir-Cur-St-N4-UT-9-23/01/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Birmingham
- Location
- Birmingham
- Worksite Name
- Curzon Station
- Contractor
- WPD
- Type of works
- Utility works / surveys
- Estimated Start Date
- 01/04/2021
- Estimated End Date
- 17/04/2021
What we are doing
Works are taking place by Western Power Distribution (WPD) on our behalf.
The proposed work is to undertake trial holes at multiple locations around the vicinity of the HS2 Curzon Street works. This work includes the excavation of material in a segregated works area and reinstatement. All works will be segregated from vehicle or pedestrian access and sign posted. Any changes to footpaths or vehicle routes will be signposted at location in line with agreed traffic management requirements. Once completed all locations will be put back as new. No outages will take place during the works.
These works are in addition to the LMJV works in the same area. All works are being coordinated with LMJV to reduce the impact on all stakeholders.
How will this affect me?
Footpath diversion and lane closure.
At all work locations, Traffic Management will be in place and this will be coordinated to make sure all appropriate lane closure or footpath diversions are in place prior to the works starting. Work locations are Park Street and Curzon Street.