Skip to main page content
View In Your Area map

Vegetation work, Station Road, Quainton

Work item: FUS_AWN_0287 EW-Fusion -Ph1-Ar-Ce-C2-Eco-36-19/11/2021

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Quainton
Contractor
EKFB JV
Type of works
Vegetation clearance
Estimated Start Date
29/11/2021
Estimated End Date
17/12/2021

What we are doing

What will we be doing?
Ahead of the main construction works in the area around Station Road, we need to carry out vegetation clearance along the highway boundary. Where appropriate some sections of vegetation will be replaced with boundary fencing, this will help keep the site secure ahead of future construction activities.
As some of these works will need to be carried out on or adjacent to the carriageway we will need to put in place two-way temporary traffic lights between 9.00am and 3.30pm.
The works will take place between 29 November until 17 December 2021.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]