Work item: HS2 MW Align Ph1 Ar Ce C1 Wat 21 10/08/2021

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Chalfont St Peter
Worksite Name
Chalfont St Giles, Chalfont St Peter
Contractor
Align JV
Type of works
Borehole works
Estimated Start Date
18/10/2021
Estimated End Date
18/11/2021

What we are doing

We will be carrying out borehole drilling in the field behind our Chalfont St Peter vent shaft on Chesham Lane on 14 October 8am to 6pm for four weeks. We may also be on site for one hour’s start up and shut down outside of those times.