Go to content
View work items map

Water monitoring borehole works at Chalfont St Peter vent shaft

Work item: HS2 MW Align Ph1 Ar Ce C1 Wat 21 10/08/2021

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Chalfont St Peter
Worksite Name
Chalfont St Giles, Chalfont St Peter
Contractor
Align JV
Type of works
Borehole works
Estimated Start Date
18/10/2021
Estimated End Date
18/11/2021

Work item details

We will be carrying out borehole drilling in the field behind our Chalfont St Peter vent shaft on Chesham Lane on 14 October 8am to 6pm for four weeks. We may also be on site for one hour’s start up and shut down outside of those times.

Download information relating to these works

We'd like your feedback

Please help us improve how we keep you informed about how we're delivering the railway by giving us feedback on your experience.

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]