Wells House Road Stairs – Footpath closure and concrete breaking
Work item: HS2-OOC - SCP-26-2740
Work Item Summary
- Project Phase
- Phase 1
- Region
- Old Oak and North Acton
- Location
- Wells House Road
- Worksite Name
- Old Oak Common
- Contractor
- BBVS JV
- Type of works
- Concrete break out, Drainage works, Footpath closures, Parking bays suspension
- Estimated Start Date
- 17/11/2026
- Estimated End Date
- 25/11/2026
What we are doing
We will be closing a small section of footpath on Wells House Road while we carry out essential drainage works on the stairs. Over the next week, we are shutting a small section of pavement on Wells House Road near the top of the stairs. At the bottom of the stairs on Old Oak Common Lane, we will also be breaking out some concrete and using a vacuum excavator on occasional days during the week. Residents will need to cross the road and use the other pavement whilst this portion of the footpath is shut. This small closure is between properties 49 to 55 Wells House Road.
Access to all properties will be maintained throughout the closure .
Working hours
- Tuesday 17 November – Wednesday 25 November 2026
- Normal working hours for site activities , and 24-hour footpath and parking bay closures
HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.