Wendover – demolition and vegetation clearance

Work item: FUS_AWN_0185 HS2-EW-Fusion -Ph1-Ar-Ce-C2-Eco-5-03/03/2021

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Wendover
Contractor
Fusion JV
Type of works
Demolition works, Environmental mitigation works, Vegetation clearance
Estimated Start Date
29/03/2021
Estimated End Date
31/05/2021

What we are doing

As part of our continuing works ahead of the construction of the railway we need to undertake some further work in your area, these works will consist of:
• Set up a temporary site compound
• Utility surveys and boundary fencing
• Preparation works
• Demolition preparation
• Bat surveys / mitigation
• Vegetation clearance