Works in Euston Approaches – spring to winter 2026

Work item: HS2-SCS-26-1768

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Euston Approaches
Worksite Name
Euston Approaches
Contractor
SCS JV
Type of works
scaffold works, Wall removal
Estimated Start Date
14/12/2025
Estimated End Date
31/12/2026

What we are doing

Restart of works in Euston Approaches

We are now restarting all works in Euston Approaches. In 2026, we’ll start planning works that were previously deferred as a result of the pause in Euston.

A broad overview of all our upcoming works in the notification below includes:

  • Parkway utility works – February to September 2026
  • Preparatory works in Zone 5 on Hampstead Road – 1 April to December 2026
  • Ongoing works in Camden Cutting to strengthen and protect the Network Rail retaining wall ahead of major excavations beginning in 2027.
  • Ongoing Hampstead Road utility works until April 2026

 

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]