UPDATED: Notice of temporary overnight closures on Drayton Lane
Work item: HS2-BBV-25-1114
Work Item Summary
- Project Phase
- Phase 1
- Region
- Staffordshire
- Location
- Drayton Lane
- Worksite Name
- Drayton Lane
- Contractor
- BBV JV
- Type of works
- Overnight road closure
- Estimated Start Date
- 24/07/2025
- Estimated End Date
- 08/08/2025
What we are doing
We are currently constructing Church Lane Overbridge in Middleton which will allow the new railway to pass underneath the lane. As part of our ongoing works, we will be installing a bridge deck as we prepare to complete the structure.
To deliver the large bridge deck beams to the site in Middleton and ensure we minimise impact on the local community we will use our haul road rather than local roads. This will include removing road signage and furniture on Drayton Lane and A453 Sutton to get the bridge deck beams on to our haul road and into Middleton. This will require temporary overnight closures of Drayton Lane.
We will have temporary overnight closures on Drayton Lane in place on 24 July and 6 August 2025 between 8pm to 2am. An additional overnight closure on 7 August 8pm to 2am will also be in place.