Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- A422, Westbury
- Worksite Name
- A422 Westbury
- Contractor
- EKFB JV
- Type of works
- Traffic management
- Estimated Start Date
- 18/07/2025
- Estimated End Date
- 12/09/2025
What we are doing
We are building a new bridge and section of road across the HS2 line on the A422 near Westbury. As part of the preparatory work, we are re-routing underground services and making new utility connections.
Four way lights will be in place on the A422 roundabout outside our compound near Westbury. The carriageway will be single lane, but the road will remain open.
EKFB will manage the lane closure and traffic lights on behalf of Anglian Water. New water pipes will be installed and connected.
Traffic Management on the section of the A422:
• Traffic lights – Monday 28 July to Friday 12 September 2025.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]