Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Hampstead Road, Lidlington Place, Stanhope Street
- Worksite Name
- Euston Approaches
- Contractor
- SCS JV
- Type of works
- Utility Works
- Estimated Start Date
- 05/01/2026
- Estimated End Date
- 30/06/2026
What we are doing
We have previously notified you of our works to remove all the utilities from Hampstead Road and redirect them across Granby Terrace bridge and over the retaining wall within our worksite. These works are required before we extend Hampstead Road bridge. After we extend Hampstead Road bridge, we will permanently reinstall the utilities back on to Hampstead Road.
The next phase of the utility diversion works will involve various utility service providers also known as statutory undertakers, working within our site, as well as on Hampstead Road, Lidlington Place and Stanhope Street to complete the final connections and energise their networks.
Download information relating to these works