Work item: HS2-EW-OTH-Ph1-Bir-Cur-St-N4-UT-16-14/06/2021

Work Item Summary

Project Phase
Phase 1
Region
Birmingham
Location
Birmingham
Worksite Name
Birmingham Curzon Street Station
Contractor
Western Power Distribution, WPD
Type of works
Utility works / surveys
Estimated Start Date
12/07/2021
Estimated End Date
12/12/2021

What we are doing

What we are doing

The proposed work is to undertake cable diversions at multiple locations around the vicinity of the HS2 Curzon Street works. This work includes the excavation of material in a segregated works area, duct installation and reinstatement. All works will be segregated from vehicle or pedestrian access and sign posted. Any changes to footpaths or vehicle routes will be signposted at location in line with agreed traffic management requirements. Once completed all locations will be put back as new. No outages will take place during the works.

To reduce the impact of works to enable the construction of HS2 other works in these areas will be taking place at the same time.

How will this affect me?

Footpath diversion and lane closure.

At all work locations, Traffic Management will be in place and this will be coordinated to make sure all appropriate lane closure or footpath diversions are in place prior to the works starting. Work locations are Dale End, Chapel St, Moor Street Queensway, Eastside City Park, Moor Street, Park Street and Curzon Street.