Skip to main page content
Inside the Long Itchington Wood Tunnel.
Inside the Long Itchington Wood Tunnel.

Long Itchington Wood Tunnel

The Long Itchington Wood Tunnel is a 1-mile (1.6km) twin-bore tunnel running beneath ancient woodland in Warwickshire. TBM Dorothy was launched in December 2021 and completed both bores of the tunnel by March 2023.

Long Itchington Wood and neighbouring Ufton Wood form a continuous block of ancient woodland, dating back to at least 1600 AD. Designated as a Site of Special Scientific Interest, they support complex ecosystems that have evolved over centuries. The Long Itchington Wood Tunnel, running beneath the woodland, is a key element of HS2’s environmental strategy to preserve and protect this vital natural habitat.

Tunnel construction

TBM Dorothy is 125 metres long and started her journey at the tunnel’s north portal in December 2021, breaking through into the south portal in July 2022. She was then relaunched in November 2022 and completed her second bore in just four months – making Long Itchington Wood Tunnel the first HS2 twin bore tunnel to be completed.

After TBM Dorothy’s first breakthrough in July 2022 the machine was taken apart and brought back to the tunnel’s north portal to start the second drive. The gantries were brought back through the tunnel while the huge cutterhead, weighing 160 tonnes and with a 10-metre diameter, was moved by road during an intricate night-time operation. The 130-tonne tail skin and eight other large pieces from the TBM’s front and middle shields were also transported by specialist equipment.

Meet our Tunnel Boring Machines 

Discover our tunnels in Warwickshire and Northamptonshire

Warwickshire and Northamptonshire tunnels map graphic
Warwickshire and Northamptonshire tunnels map graphic

Internal fit-out

The tunnel is the first deep tunnel on the high-speed route to complete its civil engineering phase. It comes before the internal fitting out of the tunnel with the complex systems needed to operate the high-speed line including the power, track and signalling.

The complex process to fully excavate two tunnel drives and the entrance sections produced around 750,000 tonnes of material, which has since been reused to build embankments along the route of the railway.

Did you know...

Long Itchington Wood Tunnel facts and figures

  • Tunnel length: 1 mile (1.6km)
  • No of tunnel cross passages: 3
  • Tunnelling construction: 12,656 segments
  • Tunnelling excavation: 750,000 tonnes of material

Long Itchington Wood Tunnel – key construction milestones

First reveal of HS2’s extensive Long Itchington Wood Tunnel north portal site in Warwickshire

December 2020 Find out more

Warwickshire residents and schools asked to name Long Itchington Wood Tunnel Boring Machine

March 2021 Find out more

Long Itchington Wood Tunnel launch site is ready for TBM assembly to begin

April 2021 Find out more

HS2 launches national vote to name Warwickshire Tunnel Boring Machine.

June 2021 Find out more

TBM Dorothy, HS2’s first Midlands tunnelling machine, is officially unveiled

October 2021 Find out more

TBM Dorothy begins her first one-mile journey under Long Itchington Wood in Warwickshire

December 2021 Find out more

New conveyor at Long Itchington Wood Tunnel site begins operating

June 2022 Find out more

TBM Dorothy completes historic first HS2 tunnelling breakthrough

July 2022 Find out more

TBM Dorothy's cutterhead completes impressive journey back to start second dig in Warwickshire

September 2022 Find out more

TBM Dorothy begins second tunnel bore under Long Itchington Wood in Warwickshire

November 2022 Find out more

Transport Secretary makes historic first journey through a completed HS2 tunnel

December 2022 Find out more

TBM ‘Dorothy’ completes second bore of Long Itchington Wood Tunnel in Warwickshire

March 2023 Find out more

Long Itchington Wood Tunnel structurally complete

February 2025 Find out more

Further information

  • Join our mailing list

    To receive email updates about the HS2 project, including how it’s being planned and constructed.

    Sign up here

  • Contact us

    If you contact the Helpdesk, our Community Engagement Advisors will try to answer your questions immediately.

    Contact us