HS2 Works Notification: Traffic management on A413 London Road, Wendover (update)

Work item: HS2-MW-EK-Ph1-Ar-Ce-C1-Traf-12-18/04/2023

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
A413
Worksite Name
A413 Small Dean
Contractor
EKFB JV
Type of works
Lane closure, Utility works / surveys
Estimated Start Date
30/05/2023
Estimated End Date
04/06/2023

What we are doing

In order to build the Small Dean Viaduct, we need to temporarily realign a section of the A413.

We are now starting phase one of this realignment which involves night time utility diversion works.

Our original notification stated these works would commence on Monday 15 May, however due to the permit to work for the area not being granted in time with the expected start date this work has now been pushed back to begin on the night of Tuesday 30 May.

We apologise for any inconvenience this may cause.

Further traffic management and temporary closures of the A413 will be required to complete these works over the coming months, details of which will be communicated in due course.

A413 London Road, lane closures will be overnight on Tuesday 30 May to Saturday 3 June – 8.30pm to 5.30am

These dates may be subject to change due to circumstances outside of our control and were correct at time of distribution.