Update on dates for 24-hour, seven days a week work below ground at the Mandeville Road Vent Shaft site, Northolt
Work item: HS2-SCS-25-1245
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Mandeville Road
- Worksite Name
- Mandeville Road worksite
- Contractor
- SCS JV
- Type of works
- 24 hour working, Concrete break out, Tunnelling works
- Estimated Start Date
- 13/10/2025
- Estimated End Date
- 10/11/2025
What we are doing
Safe stop down to SCS works from 10 October
Safety is our number one priority at HS2. Following an incident that occurred at the Green Park Way site in Ealing, works are being safely halted across the London Tunnels section of the route, including sites in Ealing. While no workers were physically harmed, our contractor, Skanska Costain STRABAG joint venture, is undertaking a comprehensive review of safety procedures and leadership on their sites before a safe restart can take place.
Works will be brought to a safe stop and will remain on hold until we’re satisfied that all appropriate measures are in place to protect the workforce. We anticipate the review may take a number of weeks depending on the area and the type of work involved.
We will provide details on when the safe stop will be in place over the course of the next week.
We’ve previously wrote you to inform you about our works from 3 October to 2 November 2025, however these dates have now changed to 11 October to 10 November.
We will work 24 hours a day, seven days a week below ground at the Mandeville Road Ventilation Shaft site.
This work is to connect the tunnel to the main shaft and needs to take place 24 hours a day for safety and engineering reasons. We will be working inside the tunnel about 25 metres below ground.
We will remove the tunnel lining segments from the upper part of the tunnel and break out the concrete between the tunnel and the bottom of the shaft. The broken concrete will then be removed through the tunnel. To reduce night-time noise, we will restrict concrete cutting and drilling activities to between 8am and 10pm daily.
For further details of above work, please see the notification below.
Note: Please be aware that we are already working 24-hour Monday to Friday, twenty one metres below ground until 13 October 2025. For details, please follow the link to Update: 24-hour work on Mondays to Fridays at Mandeville Road site extended until 3 October 2025
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]