Updated notice of temporary traffic lights and overnight closures of Long Itchington Road
Work item: HS2-BBV-25-1254
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Long Itchington
- Worksite Name
- Fosse Way
- Contractor
- BBV JV
- Type of works
- Road closure, Traffic management
- Estimated Start Date
- 13/10/2025
- Estimated End Date
- 14/11/2025
What we are doing
We are progressing construction of Fosse Way Overbridge and the new road realignment, including preparing and completing utility diversion and reconnection works. To do this safely, we will install temporary traffic lights and overnight closures of Long Itchington Road.
We recently communicated the temporary traffic lights and overnight closures for Long Itchington Road were due to start on Monday 29 September. We have postponed the start of the works until mid-October 2025.
The works will be carried out in two phases:
Phase one: Monday 13 October to Friday 17 October 2025. Overnight road closure from 7pm to 6am and temporary multi-way traffic lights from 6am to 7pm. A fully signposted diversion will be in place.
Phase two: Monday 10 November to Friday 14 November 2025. Temporary multi-way traffic lights 24/7.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]