Updated notice of temporary traffic lights and overnight closures of Long Itchington Road

Work item: HS2-BBV-25-1254

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire
Location
Long Itchington
Worksite Name
Fosse Way
Contractor
BBV JV
Type of works
Road closure, Traffic management
Estimated Start Date
13/10/2025
Estimated End Date
14/11/2025

What we are doing

We are progressing construction of Fosse Way Overbridge and the new road realignment, including preparing and completing utility diversion and reconnection works. To do this safely, we will install temporary traffic lights and overnight closures of Long Itchington Road.

We recently communicated the temporary traffic lights and overnight closures for Long Itchington Road were due to start on Monday 29 September. We have postponed the start of the works until mid-October 2025.

The works will be carried out in two phases:

Phase one: Monday 13 October to Friday 17 October 2025. Overnight road closure from 7pm to 6am and temporary multi-way traffic lights from 6am to 7pm. A fully signposted diversion will be in place.

Phase two: Monday 10 November to Friday 14 November 2025. Temporary multi-way traffic lights 24/7.