Notice of temporary traffic lights and overnight closures of Long Itchington Road

Work item: HS2-BBV-25-1254

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire
Location
Long Itchington
Worksite Name
Fosse Way
Contractor
BBV JV
Type of works
Road closure, Traffic management
Estimated Start Date
29/09/2025
Estimated End Date
17/10/2025

What we are doing

We are progressing construction of Fosse Way Overbridge and the new road realignment, including preparing and completing utility diversion and reconnection works. To do this safely, we will install temporary traffic lights and overnight closures of Long Itchington Road.

The works will be carried out in two phases:

Phase one:

Monday 29 September to Friday 3 October2025.

Overnight road closure from 7pm to 6am and temporary multi-way traffic lights from 6am to 7pm. A fully signposted diversion will be in place.

Phase two:

Monday 13 October to Friday 17 October 2025.  Temporary multi-way traffic lights 24/7.