Works to build headhouse base slab at Mandeville Road site, Northolt

Work item: HS2-SCS-25-1087

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Mandeville Road
Worksite Name
Mandeville Road
Contractor
SCS JV
Type of works
Concrete break out, Concrete pours
Estimated Start Date
07/07/2025
Estimated End Date
19/12/2025

What we are doing

From 7 July to 19 December 2025 we will continue works to build the base slab for the headhouse.

We will use handheld tools to cut the existing concrete surface and an excavator to break up the concrete.

We’ll then install reinforced steel and pour concrete to build the base slab.

You may notice some noise and vibration during these works. We will use noise reducing barriers, where possible, and water sprays to reduce dust.

We apologise for any disruption these works may cause.