Notice of Ashow Road and Crewe Lane closures, Stoneleigh
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-30-26/01/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Stoneleigh
- Contractor
- BBV JV
- Type of works
- Drainage installation, Traffic management
- Estimated Start Date
- 27/02/2023
- Estimated End Date
- 06/04/2023
What we are doing
BBV need to install new pipes and infrastructure for the permanent drainage, required on both Ashow Road and Crewe Lane, this drainage will enable further works in the future.
We will be carrying out multiple phases of work over six weeks from 27 February 2023 to 6 April 2023 detailed below.
Phase 1: 27 February to 6 March 2023, three-way temporary traffic lights at the Junction of Ashow Road and Crewe Lane to enable works to be undertaken safely in the verge on the south side of Ashow Road and Crewe Lane.
Following an overrun on other highway works in the area, we need to delay the start of the phase 2 closure from 6 March to 13 March 2023. The completion date will remain the same.
Phase 2: 13 March to 27 March 2023, there will be a full road closure of Crewe Lane from the junction of Ashow Road. During this road closure there will also be two-way traffic signals on Ashow Road. This will provide a safe working area for works in the carriageway of Crewe Lane.
Phase 3: 27 March to 3 April 2023, three-way temporary traffic lights at the Junction of Ashow Road and Crewe Lane while we install new drainage in the verge on the north side of Ashow Road and Crewe Lane.
Phase 4: 3 April to 6 April 2023, two-way temporary traffic lights on Ashow Road while the drainage is installed in the verge and carriageway.
Our working hours will be from 8am to 6pm Monday to Friday. Our workforce maybe on site one hour before and one hour after to set up and secure our equipment.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]