Updated notice of works on Bromford Drive, Birmingham

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-17-22/04/2024

Work Item Summary

Project Phase
Phase 1
Region
Birmingham, West Midlands
Location
Bromford
Contractor
BBV JV
Type of works
Utility works / surveys
Estimated Start Date
20/05/2024
Estimated End Date
19/07/2024

What we are doing

*Updated notice

We contacted you in May providing you with details of ground investigation and survey work taking place on and near Bromford Drive. We have reviewed our work within this area and need additional time to complete it, helping us minimise the level of vegetation clearance. Our new programme dates are:

  • Single lane closure on Bromford Drive and installation of temporary traffic lights: 24 June to 19 July
  • Footpath closures near Bromford Drive: from 20 May until 28 June.

As we continue our preparation for the construction of the Bromford Tunnel, we will be carrying out preparatory and ground investigation works, which will include drilling. This is to give us an understanding of ground conditions and to help us better plan our upcoming works.

Between Monday 24 June to Friday 19 July temporary traffic lights will be installed on a section of Bromford Drive, to enable mobilisation, and demobilisation of equipment. These traffic lights will be put in place for 24 hours a day. There will be welfare facility on Bromford Drive within our working area.
We will need to close some sections of the footpath near Bromford Drive, to ensure the safety of the public. We will install closures from Monday 20 May to Friday 19 July. In addition to the closure, we will be installing two small cabins for our staff.
Our working hours are still from 8am until 6pm. Our workforce may be on site up to an hour before and after to set up and secure our equipment.

As we continue our preparation for the construction of the Bromford Tunnel which will be passing near you, we will be carrying out preparatory and site investigation works, which will include drilling. This is to give us an understanding of ground conditions and to help us better plan our upcoming works.

To complete the survey work, we will be working from Monday 20 May for 5 weeks, from 8am to 6pm.
Our workforce may be on site up to an hour before and after to set up and secure our equipment.

Between Monday 20 May to Friday 24 May 2024, as well as Monday 24 June to Friday 28 June 2024, temporary traffic lights will be installed on a section of Bromford Drive, shown on map one on the following page, to enable mobilisation, and demobilisation of equipment.

Additionally, we will need to close some sections of the footpath near Bromford Drive, shown on map 2 overleaf. We will install closures from Monday 20 May for five weeks. Closures will remain in place throughout the period of works, to ensure the safety of the public. In addition to the closure, we will be installing two small cabins for our staff.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]