Update: Notice of gas diversion works on West Gate

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-UT-04/01/2024

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing, London
Location
A40, Western Avenue
Worksite Name
Western Avenue, Westgate
Contractor
SCS JV
Type of works
Utility works / surveys
Estimated Start Date
20/01/2024
Estimated End Date
24/02/2024

What we are doing

Following our recent ground assessments of the area, we need to upgrade and divert the gas mains to strengthen and protect them ahead of tunnelling works.

From 20 to 26 January 2024, the works will take place overnight between 7pm and 5am.

From 29 January to 24 February 2024, the works will take place between 8am and 8pm.

We’ll need to make temporary changes on West Gate to ensure the safety of the public and our staff.

From 20 January to 24 February 2024, there will be traffic management in place. This will include a footpath closure, lane closures and parking bay suspensions.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]