Update: Notice of gas diversion works on West Gate
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-UT-04/01/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing, London
- Location
- A40, Western Avenue
- Worksite Name
- Western Avenue, Westgate
- Contractor
- SCS JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 20/01/2024
- Estimated End Date
- 24/02/2024
What we are doing
Following our recent ground assessments of the area, we need to upgrade and divert the gas mains to strengthen and protect them ahead of tunnelling works.
From 20 to 26 January 2024, the works will take place overnight between 7pm and 5am.
From 29 January to 24 February 2024, the works will take place between 8am and 8pm.
We’ll need to make temporary changes on West Gate to ensure the safety of the public and our staff.
From 20 January to 24 February 2024, there will be traffic management in place. This will include a footpath closure, lane closures and parking bay suspensions.