Update: Utility works on Greenford Road, Ealing

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-1-23/02/2023_02

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Greenford Road
Worksite Name
South Ruislip
Contractor
SCS JV
Type of works
Utility works / surveys
Estimated Start Date
03/07/2023
Estimated End Date
31/07/2023

What we are doing

What we are doing
We will be undertaking utility works on Greenford Road to install a protective lining in the sewer system. This work follows on from the initial surveys and preparatory work undertaken in March.

We will be installing the lining on Greenford Road from 3 to 31 July 2023 in the area shown on the map overleaf, Monday to Saturday 8am to 6pm.  However there will be no noisy works after 1pm on Saturdays.

Traffic management with a lane closure and additional traffic lights will be in place 24 hours a day for the duration of these works.

How these works might affect you
We will be using an excavation vacuum to remove the soil during these works, and we expect that this will create some noise. We will however limit its use as much as possible. We will use noise reducing barriers to minimise disruption.

We would like to apologise in advance for the disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way.

We will ensure that disruption is kept to a minimum.