Weekend works at the Granby Terrace bridge – 11 November to 10 December

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Site-1-10/11/2023

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Granby Terrace bridge
Worksite Name
Euston Approaches
Contractor
SCS JV
Type of works
Enabling works, Extended working hours
Estimated Start Date
11/11/2023
Estimated End Date
10/12/2023

What we are doing

Weekend work at track-level next to Granby Terrace bridge – 11 November to 10 December

We are currently building a wall at track-level between the Network Rail and future HS2 tracks. This wall will also act as one of the supports for the new section of Granby Terrace bridge. For safety, we can only work on this wall during a rail possession when the tracks next to site are not in use.

We will work from 8am to 8pm on 11 and 12 November to build framework and pour the concrete to construct the wall. We will also need to work overnight during the following rail possession weekends from 10pm to 7am.

  • 2 to 3 December
  • 9 to 10 December

There may be periods of increased noise as we break out small sections of concrete next to the railway. We will monitor the level of noise from these works closely.

Overnight work on Granby Terrace bridge – 25 to 26 November

We will work overnight from 9pm Saturday 25 November to 11am Sunday 26 November, to install temporary supports on the parapet wall on Granby Terrace bridge. For safety, we can only carry out this work when the tracks below are not in use.

If we cannot complete the work on 25 to 26 November, we will complete it the following weekend from 2 to 3 December. This work will not be noisy or disruptive.

Other weekend and extended hours works in Euston Approaches include:

  • Ongoing weekend site maintenance and surveys/monitoring on track-level
  • Overnight hoarding maintenance on Hampstead Road – 18 to 19 November
  • Overnight Maintenance and installation of traffic cameras – 20 to 21 November

For further details of above works please see notification below.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]